Northern Star Flags KCGM at Low End of 550-650koz Guidance

Northern Star says KCGM produced 15.3koz in October as plant commissioning lagged, tracking to the low end of guidance, while Hemi won primary approvals.

By Digifin Pty Ltd · About this coverage

Key Points

  • KCGM produced 15.3koz of gold in October from 766kt milled, below plan
  • KCGM production tracking towards the lower end of 550-650koz guidance
  • FY27 Group guidance unchanged at 1,500–1,650koz gold sold, weighted to the second half
  • Hemi Gold Project received primary Federal and State environmental approvals
Northern Star Resources Ltd (ASX:NST)

About Northern Star (ASX:NST)

Northern Star Resources Ltd is an ASX-listed gold producer headquartered in Perth. It operates gold mines and processing plants in Western Australia, including Kalgoorlie Consolidated Gold Mines, and the Pogo mine in Alaska. It earns its revenue from the sale of gold.

Northern Star (ASX:NST) issued the update because commissioning of the expanded KCGM processing plant has not gone to plan, leaving KCGM production tracking towards the lower end of its FY27 guidance range.

KCGM produced 15.3koz of gold in October from 766kt milled, below plan. Plant availability and throughput were affected by commissioning issues, including intermittent problems with the mill motor control systems, now addressed, and minor rectification work on selected equipment, which is ongoing. A planned 3.5-day maintenance shutdown was completed on 30 October. KCGM production is tracking towards the lower end of the 550-650koz guidance range, with the outcome depending primarily on the timing and pace of ramp-up over the remainder of FY27. The company says plant performance in November, month to date, shows greater stability, and that mining is performing to plan with ROM stockpiles building. FY27 Group production guidance is unchanged at 1,500–1,650koz gold sold, weighted to the second half. Separately, the Hemi Gold Project has received its primary Federal approval under the EPBC Act and State approval under Part IV of the EP Act.

Hemi still requires secondary approvals under the Mining Act 1978, the Rights in Water and Irrigation Act 1914 and Part V of the EP Act, and its schedule remains subject to outstanding land access and regulatory processes. No November production figure is given.

Back to all ASX Company News

Source: Northern Star Resources Ltd (ASX:NST), 9 November 2026. Summary content supplied by Digifin Pty Ltd.

News summary only, not financial advice. It does not consider your objectives, financial situation or needs.

Monday, 9 November 2026

Also summarised today

All ASX Company News
ASX: ANZFinancials

ANZ FY26 Cash Profit Up 31% to $7,591 Million

ANZ's FY26 Cash Profit rose 31% to $7,591 million, or 10% excluding FY25 significant items, with a final dividend of 83 cents per share franked at 80%.

9 Nov, 7:30 am AEDT
ASX: DNLMaterials

Dyno Nobel FY26 Explosives EBIT $485m, Guides $515m-$555m

Dyno Nobel's FY26 explosives underlying EBIT rose to $485m, statutory net profit was $66m after IMIs, and FY27 underlying EBIT guidance is ~$515m-$555m.

9 Nov, 8:29 am AEDT
ASX: EOSIndustrials

EOS Wins US$16m Middle East Counter-Drone Order

Electro Optic Systems won a US$16 million (approximately A$23 million) counter-drone order from a Middle Eastern nation state, its first sale to that country.

9 Nov, 8:22 am AEDT
ASX: GMGReal Estate

Goodman and Digital Realty Take 9.9% Stake in NEXTDC

Goodman and Digital Realty bought a 9.9% stake in NEXTDC at an average $9.22 a share via a 50:50 vehicle, with no present intention to make a takeover offer.

9 Nov, 9:17 am AEDT
ASX: IGOMaterials

IGO Ends Nova Mining Above Nickel Guidance

IGO has concluded mining at Nova with 21,340t of nickel, 7% above the top end of guidance, at a cash cost of A$3.90/lb, ahead of its sale to Global Lithium.

9 Nov, 9:06 am AEDT
ASX: KAREnergy

Karoon Moves Neon Into FEED With US$800-950m Phase 1

Karoon has moved its revised Neon oil project offshore Brazil into FEED, with Phase 1 capital costs of US$800-950 million and first oil targeted for 2030.

9 Nov, 9:01 am AEDT
ASX: SIQIndustrials

Smartgroup Expects CY2026 NPATA of $92-94m

Smartgroup expects CY2026 NPATA of $92-94m after Q3 novated leasing settlements rose 31% and orders rose 33%, and it targets mid-40s EBITDA margins in 2027.

9 Nov, 8:46 am AEDT
ASX: SSMIndustrials

Service Stream to Buy Programmed for $975 Million

Service Stream will buy Programmed from Persol for $975 million, funded by a $475 million equity raising at $2.03 a share and debt, subject to ACCC approval.

9 Nov, 9:04 am AEDT
ASX: VNTIndustrials

Ventia Targets $60m Savings, Flags Lower 2H26 Revenue

Ventia will move to three operating sectors from 1 December 2026, targeting at least $60 million in annualised savings, and expects lower 2H FY26 revenue.

9 Nov, 8:13 am AEDT