Brightstar Goldfields Build Reaches 50% EPC Earned Value

Brightstar said its Goldfields Project build is at 50% EPC earned value and on track for first gold in June 2027, and it has bought a 223-room Laverton camp.

By Digifin Pty Ltd · About this coverage

Key Points

  • Overall EPC earned value at 50%, with the 90% engineering milestone achieved in October
  • First gold at the Laverton plant still targeted for June 2027
  • Boomers Mining Accommodation Camp in Laverton acquired, adding 223 rooms
  • First blast at the Lord Byron open pit targeted for the December quarter
Brightstar Resources Limited (ASX:BTR)

About Brightstar Resources (ASX:BTR)

Brightstar Resources Limited is an ASX-listed gold company headquartered in Perth. It holds gold projects in Western Australia, including the Sandstone Gold Project.

Brightstar gave a monthly construction update on its 100%-owned Goldfields Project in Western Australia, saying the 1.5Mtpa Laverton processing plant remains on schedule and within budget for first gold in June 2027, and disclosed that it has bought an accommodation camp in Laverton.

Overall EPC earned value has reached 50% completion and the 90% engineering milestone was achieved in October. Major SAG mill components have arrived on site, primary crusher concrete is complete, two leach tanks have been fabricated to full height and two production bores have been flow tested. Brightstar has completed the acquisition of the Boomers Mining Accommodation Camp in Laverton, which has 223 rooms, to house the workforce through peak plant construction and future shutdowns and to serve as a base for operations. At the Lord Byron open pit, grade control drilling has started and drill and blast contractor Aquirian Limited has mobilised, with the first blast targeted for the December quarter, which the company says is ahead of schedule. Open pit mining is targeted to begin early in the March quarter of 2027. Brightstar says the A$82 million placement announced on 27 October 2026 for the Sandstone Project does not change the Goldfields budget or schedule.

The release does not state the project budget, spending to date or the price paid for the Boomers camp. The on schedule and on budget description is the company's own assessment.

Back to all ASX Company News

Source: Brightstar Resources Limited (ASX:BTR), 10 November 2026. Summary content supplied by Digifin Pty Ltd.

News summary only, not financial advice. It does not consider your objectives, financial situation or needs.

Tuesday, 10 November 2026

Also summarised today

All ASX Company News
ASX: 360Information Technology

Life360 Q3 Revenue Up 40% to US$174.1 Million

Life360 lifted Q3'26 revenue 40% to US$174.1 million and narrowed FY'26 revenue guidance to US$665 million to US$681 million, with Paying Circles up 26%.

10 Nov, 8:24 am AEDT
ASX: 3DAIndustrials

Amaero Q3 Revenue Up 35% to US$4.1 Million

Amaero lifted Q3 2026 revenue 35% to US$4.1 million with a net loss of US$9.1 million, and guided fourth quarter revenue of US$4.5 million to US$5.0 million.

10 Nov, 9:03 am AEDT
ASX: BXBIndustrials

Brambles Prices €850 Million Green Bond Due 2034

Brambles has priced a €850 million Green Bond due 2034 with a 4.375% coupon under its European Medium-Term Note programme, with settlement expected 16 November.

10 Nov, 8:51 am AEDT
ASX: LINMaterials

Lindian Signs Binding Monazite Offtake Term Sheet

Lindian signed a binding term sheet to supply Kangankunde Monazite Concentrate to a refining group, with 10,000dmt in Stage 1 and 20,000dmt a year in Stage 2.

10 Nov, 9:00 am AEDT
ASX: MNDIndustrials

Monadelphous Forecasts 1H Profit of $80m to $85m

Monadelphous forecast half-year net profit after tax of $80 million to $85 million on revenue of about $1.7 billion, and has won $830 million of new contracts.

10 Nov, 8:19 am AEDT
ASX: OFXFinancials

OFX 1H27 Revenue Falls 15.5%, Equals Talks Continue

OFX reported 1H27 fee and trading income down 15.5% to $92.2 million and a statutory loss of $6.7 million, with Equals talks ongoing on a non-exclusive basis.

10 Nov, 8:21 am AEDT
ASX: RHIMaterials

Red Hill Grants Option Over Pannawonica for 1.5% Royalty

Red Hill Minerals gave Arrow Minerals a 12-month option to buy its Pannawonica Iron Project for $1,000,000 plus an uncapped 1.5% Gross Revenue Royalty.

10 Nov, 8:26 am AEDT
ASX: SLCCommunication Services

Superloop Guides FY27 Underlying EBITDA of $148m-$156m

Superloop guided FY27 Underlying EBITDA of $148m to $156m, up 21% to 27% on FY26, with group customers up 18.5k to 954k and capex of $58m to $62m expected.

10 Nov, 8:16 am AEDT
ASX: VULMaterials

Vulcan Mobilises Second Drill Rig at Lionheart

Vulcan Energy is mobilising a second in-house drill rig to Lionheart's Trappelberg site after investing about €51m in two rigs, targeting production in H2 2028.

10 Nov, 8:20 am AEDT

Announcement summaries are published each trading day. General advice only.

Copyright © 2026 SureStone Capital