By Digifin Pty Ltd · About this coverage
Key Points
- 85 MW South Erregulla Power Plant energised on 20 November 2026
- AEMO hold-point testing expected to take approximately six to eight weeks
- Final forecast cost of $187 million against $137 million at FID
- Illustrative capacity revenue of approximately $39 million a year for Capacity Year 2029

About Strike Energy (ASX:STX)
Strike Energy Limited is an ASX-listed gas exploration, production and gas-to-power company headquartered in Perth. It holds exploration and production acreage across the onshore Perth Basin in Western Australia, where its interests include the Walyering and West Erregulla gas fields and the South Erregulla project. Its gas is directed at the Western Australian domestic market.
Strike Energy (ASX:STX) announced that its 85 MW South Erregulla Power Plant (SEPP) has been energised and connected to Western Australia's South West Interconnected System (SWIS), completing construction and moving the plant into grid testing.
Energisation was completed on 20 November 2026 with Western Power. AEMO hold-point testing, forecast to take approximately six to eight weeks, will step output from 10 MW to the full 85MW, ahead of commercial operations in late January 2027. Strike has invested $187 million, excluding capitalised interest, comprising $153 million for the plant, $32 million for Western Power connection infrastructure and $2 million for operational readiness. That final forecast cost compares with $137 million at FID in November 2024, and the company attributes the $48 million increase to the expanded grid connection scope, additional upstream and well workover activity, engineering costs, inflation and delayed completion. The plant has secured Capacity Credits through Capacity Year 2029. For that capacity year, Strike gives illustrative figures of approximately $39 million a year of capacity revenue and approximately $36-$42 million a year of electricity sales revenue.
Commercial operations depend on AEMO and Western Power approving each hold-point stage. The revenue figures are illustrative, electricity sales are not contracted, and about $9 million of the $187 million is still to be spent.
Source: Strike Energy Limited (ASX:STX), 26 November 2026. Summary content supplied by Digifin Pty Ltd.
News summary only, not financial advice. It does not consider your objectives, financial situation or needs.