Key Points
- Preliminary approval of a major Environmental Authority amendment for Capricorn Copper
- Approval covers Tailings Storage Facility 3 and other infrastructure needed for a restart
- 20-business day objection period in which the matter can be referred to the Land Court
- Restart DFS on track for completion by the end of 2026; funding proposals under evaluation
- Golden Grove October ore mined of 156kt, highest monthly volume in over three years

About 29Metals (ASX:29M)
29Metals Limited is an ASX-listed base metals mining company headquartered in Melbourne. It operates the Golden Grove copper and zinc mine in Western Australia and owns the Capricorn Copper mine in Queensland, where operations are suspended.
29Metals (ASX:29M) has received preliminary approval for a major amendment to the Capricorn Copper Environmental Authority, allowing construction of a new tailings storage facility and the other infrastructure needed to restart operations.
The approval from the Queensland Department of Environment, Tourism, Science and Innovation provides for Tailings Storage Facility 3 and all other required infrastructure for a restart. Alongside the draft Decision Notice, the department issued a Referral Notice that opens a 20-business day objection period in which the matter can be referred to the Land Court. A new Water Treatment Plant is also planned, detailed designs are being finalised, and the company expects to tender for construction in 2027. 29Metals expects to respond to the federal Request for Information on its EPBC referral before year end, and describes EPBC as the final approval required for a restart. The restart Definitive Feasibility Study remains on track for completion by the end of 2026, and the company is evaluating streaming, royalty and joint-venture proposals to fully fund the restart and enable a Final Investment Decision. At Golden Grove, October ore mined was 156kt, the highest monthly volume in over three years, against 148kt in September, and the mill ran at an annualised rate of 1.6Mtpa.
The approval is preliminary and open to objection, EPBC approval is still outstanding, restart funding is not secured, no Final Investment Decision has been taken, and the release does not state restart capital costs.
Source: 29Metals Limited (ASX:29M), 17 November 2026. Summary content supplied by Digifin Pty Ltd.