Grange Approves A$287m Savage River Underground Mine

Grange Resources made a final investment decision on a Sub-Level Cave underground mine at Savage River, with A$287m capex and a project NPV of A$357 million.

By Digifin Pty Ltd · About this coverage

Key Points

  • Final Investment Decision for the North Pit Underground Project as a Sub-Level Cave
  • Underground capital expenditure of A$287 million and ~10 year mine life
  • Project NPV of A$357 million (8.3% real, after tax) and IRR of 43% at US$90/t
  • Underground mining forecast to commence in Q1 2027, extending supply continuity to 2035
  • Block Cave option preserved, with a decision to be made at a future date
Grange Resources Limited (ASX:GRR)

About Grange Resources (ASX:GRR)

Grange Resources Limited is an ASX-listed iron ore company headquartered in Burnie, Tasmania. It operates the Savage River magnetite mine and the Port Latta pellet plant in north-west Tasmania, producing iron ore pellets for steelmakers.

Grange Resources (ASX:GRR)' board approved a lower-capital underground mine at its Savage River iron ore pellet operations in Tasmania to extend production, after the larger Block Cave design could not be funded at the required scale.

The North Pit Underground Project will proceed as a Sub-Level Cave, at a significantly lower initial capital requirement than the previously considered Block Cave, which remains an option for a future decision. Underground capital expenditure is A$287 million, with A$234 million of sustaining capital over a mine life of ~10 years. Base case economics, at a flat US$90/t for 62% Fe fines and A$1.00 = US$0.68, give a project NPV of A$357 million (8.3% real, after tax) and an IRR of 43%, with an average C1 cash cost of A$132 per tonne and all-in cost of A$164 per tonne against an average product price of A$181. All environmental approvals are in place. Underground mining is forecast to start in Q1 2027, extending production and pellet supply continuity to 2035. Grange cites weaker iron ore prices, rising costs and reduced risk appetite as the reasons the Block Cave could not be funded.

Mining contracts have not yet been awarded. The release describes the project as projected to be fully funded in its highlights but largely self-funded elsewhere. Extension beyond 2040 depends on a future Block Cave or open-pit decision not yet taken.

Back to all ASX Company News

Source: Grange Resources Limited (ASX:GRR), 14 October 2026. Summary content supplied by Digifin Pty Ltd.

News summary only, not financial advice. It does not consider your objectives, financial situation or needs.

Wednesday, 14 October 2026

Also summarised today

All ASX Company News
ASX: EVNMaterials

Evolution Mining Holds FY27 Guidance After Slower Start

Evolution Mining produced 154koz of gold and 18kt of copper in the September quarter at an AISC of $1,653/oz and kept FY27 Group guidance across all measures.

14 Oct, 8:41 am AEDT
ASX: FBUMaterials

Fletcher Building Q1 FY27 Volumes Up in Most Units

Fletcher Building said Q1 FY27 sales volumes were ahead of a year earlier in most units, but expects minimal half-year earnings from Residential & Development.

14 Oct, 7:30 am AEDT
ASX: FRIReal Estate

Finbar Completes Garden Towers, Settlements to Begin

Finbar has completed its 342-lot Garden Towers project in East Perth with titles issued and 82% sold, and expects settlements to contribute to H1 FY27 results.

14 Oct, 8:22 am AEDT
ASX: IAGFinancials

IAG Offers NRMA WA Policy Sale to Win RAC Alliance Approval

IAG has offered to sell NRMA Insurance WA home and motor renewal rights and invest $20m in WA communities as it seeks ACCC approval for its RAC alliance.

14 Oct, 8:38 am AEDT
ASX: MCYUtilities

Mercury Q1 FY27 Trading Margin Up 19% Despite Low Hydro

Mercury's first-quarter FY27 trading margin rose 19% to $445 million as new wind and geothermal generation offset hydro volumes that fell 24% on low inflows.

14 Oct, 7:30 am AEDT
ASX: PDNEnergy

Paladin Q1 Output Falls, FY2027 Uranium Guidance Kept

Paladin produced 1.00Mlb of U3O8 at Langer Heinrich in the September quarter after a shutdown, and reaffirmed FY2027 production guidance of 5.1 to 5.6Mlb.

14 Oct, 8:57 am AEDT
ASX: PPSFinancials

Praemium Platform FUA Hits $34.4b as Net Flows Halve

Praemium's platform FUA rose 7.4% to $34.4 billion in the September quarter, while net flows fell 50.2% to $274 million amid softer industry inflow conditions.

14 Oct, 9:22 am AEDT
ASX: RIOMaterials

Rio Tinto Q3 2026 Output Steady, Guidance Maintained

Rio Tinto kept 2026 production guidance in Q3 as Oyu Tolgoi copper rose 27% and iron ore sales rose 3%, with lithium now expected at the low end of its range.

14 Oct, 8:23 am AEDT
ASX: VALMaterials

Valiant Gold Keeps H2 FY27 Target for Comet Restart

Valiant Gold has dewatered Comet to 170 metres below surface and installed key site facilities, keeping its target for first production at Comet in H2 FY27.

14 Oct, 8:49 am AEDT

Announcement summaries are published each trading day. General advice only.

Copyright © 2026 SureStone Capital